What defines a robot pick and place cycle time of 5 seconds

Servo and stepper motion Published 7 min read By AutomateDirectUSA engineering team

Short answer

A speed setting cannot guarantee a 5-second pick and place cycle. Define which interval you are timing, measure it with a start signal and a completion signal, subtract the timestamps, then split the result into motion and non-motion time and adjust one motion setting at a time. Treat 5 seconds as a deadline, not an exact duration to synchronize.

On this page
  1. Define which interval the five seconds applies to
  2. Measure the cycle with two signals
  3. Budget the measured interval before changing anything
  4. Let the move length decide between speed and acceleration
  5. Change one setting at a time and re-measure
  6. The decision for each case
  7. Questions asked

The number that decides a robot pick and place cycle time is not the speed setting: it is the measured interval between a start event and a completion event, plus the budget you assign to each part of that interval. The speed dial cannot promise a duration - the measured time also depends on the route, acceleration and deceleration, grip and release, waits, and where you declare the cycle finished. The method that works: define which interval the five seconds applies to, measure it with two signals and a timestamp subtraction, split the measured time into motion and non-motion portions, then change one motion setting at a time and re-measure. The worked example below times a P1-to-P3 transfer that measures 6.40 s against a 5.00 s deadline and shows which change gets it under.

Define which interval the five seconds applies to #

Pick from P1 and place at P3 in 5 seconds leaves two decisions open, and each one changes the measurement.

Transfer or repeat cycle. Timing from the start of the pick move to confirmed release at P3 measures the transfer. Starting one cycle earlier and stopping after the robot is back at the next pickup measures the repeat cycle. Both are legitimate; resolve with the sequence drawing which one the customer means before tuning, because the return leg can be half the budget.

Deadline or synchronized finish. 'In 5 seconds' normally means a deadline: completing at or before the target passes, and an early finish is a good result. A synchronized finish - the part arriving exactly on the target time - is a different requirement that needs deliberate waiting, and you decide that once the measurement works.

Definition What gets timed What the number means
Transfer only Pick move start to confirmed release at the place position Transfer time against the deadline
Full repeat cycle Cycle start to back at the next pickup position Station takt for one part
Deadline (the usual case) Completion any time up to the target Pass or fail; early is fine
Synchronized finish Completion exactly at the target Deliberate waiting must be added

Commit to one row before touching a speed setting. If the pickup is from a moving conveyor rather than a fixed position, the interval is no longer a fixed-position transfer - readiness waits and tracking ramps add variability, and conveyor tracking error during start and stop ramps covers how ramps show up in that measurement.

Measure the cycle with two signals #

Edit the robot program to emit a signal at the start of the defined operation and a second signal after its completion, and send both to something that can timestamp them - a PLC input, the controller's trace function, or a logger. The robot's motion is untouched; the signals only make the timing observable.

  1. Put the start signal at the agreed sequence boundary: the first motion of the timed transfer, not an unrelated operator command.
  2. Put the completion signal after the agreed placement condition. If release is part of the definition, arrival at the place position is not completion - the released part is.
  3. Capture each transition once per cycle and pair every completion with its own start.
  4. Compute elapsed time = completion timestamp - start timestamp, with both timestamps from the same time base.
  5. Run one controlled cycle and confirm exactly one start, one completion, and a positive duration before trusting the number.

A start fired on the wrong boundary, or a completion fired on arrival when the definition includes release, is the fastest way to tune to the wrong target.

Budget the measured interval before changing anything #

The numbers below are a worked example for one illustrative cell; take your own durations from the signal measurement.

Measured result: elapsed time 6.40 s against a 5.00 s deadline, so 1.40 s has to come out. Split it:

Segment Example duration Kind
Approach move to the pickup 1.20 s Motion
Grip and grip confirmation 0.30 s Non-motion
Transfer from P1 to P3 2.60 s Motion
Release at the place position 0.20 s Non-motion
Return toward the next pickup 1.90 s Motion
Wait for the part-present signal 0.20 s Non-motion

Check the arithmetic: 1.20 + 0.30 + 2.60 + 0.20 + 1.90 + 0.20 = 6.40 s, of which motion is 5.70 s and non-motion is 0.70 s. Where segments overlap in the real sequence, follow the actual sequence instead of adding durations twice. Confirm the speed override is at its full value first - a partial override scales every move and hides the programmed settings.

The budget gives the first decision: the wait for the part-present signal is removable by requesting that signal earlier in the sequence, which brings the cycle to 6.20 s - still 1.20 s over - while grip confirmation and release stay, because the process needs them.

Let the move length decide between speed and acceleration #

Speed and acceleration shape the trajectory; neither assigns a total duration, and raising the wrong one does nothing. For a segment where the axis accelerates over the first half of the distance and decelerates over the second half - the normal case for a robot's point-to-point move, which never reaches cruise speed - kinematics give t = 2·√(d/a), with d the segment distance in meters, a the acceleration in m/s² and t the segment time in seconds. The implied acceleration is a = 4·d/t² and the peak speed reached is 2·d/t.

Transfer segment of the example: d = 0.9 m and t = 2.60 s, so a = 4 × 0.9 / 2.60² = 3.6 / 6.76 = 0.53 m/s² and peak speed = 2 × 0.9 / 2.60 = 0.69 m/s. With a programmed top speed of 1.0 m/s (an example value), the axis never gets near it - raising the speed setting to 2.0 m/s changes this segment by exactly nothing. Doubling the set acceleration to 1.06 m/s² (an example; take the dynamics allowed for your payload from the robot datasheet) divides the segment time by √2, about 1.41: 2.60 / 1.41 = 1.84 s, which takes the cycle from 6.20 s to 5.44 s.

Return leg: d = 0.5 m and t = 1.90 s give a = 4 × 0.5 / 1.90² = 2.0 / 3.61 = 0.55 m/s². Doubling it: 1.90 / 1.41 = 1.35 s, and the cycle lands at 4.89 s - under the 5.00 s deadline with 0.11 s of margin.

Decision rule: compute 2·d/t for every long segment. If the peak speed sits below the programmed limit, the segment is acceleration-limited, so raise acceleration. If it sits at the limit, the segment is speed-limited, so raise speed or shorten the path. The figures here are calculated examples for these inputs, not measured results; verify each segment with your own signal measurement.

Change one setting at a time and re-measure #

  1. Run the defined route with the intended payload and approved settings, and record the baseline from the two signals.
  2. Remove programmed waits and redundant travel only after checking their process purpose: grip confirmation, clearance moves and placement conditions stay. In the example, the part-present wait went because the signal could be requested earlier, not because a check was dropped.
  3. Change one motion setting - acceleration on an acceleration-limited segment first - then re-measure with the same two signals at the same boundaries, so the effect of that one change stays visible.
  4. Check quality after every change: missed pickups, unstable load, and placement accuracy. A faster approach changes the part's attitude at handover, and placement position varies with the pickup angle (why placement position varies with the pickup angle), so re-check the placement offset, not just the clock.
  5. Stop when the deadline is met with margin; the example settles at 4.89 s, which leaves room for cycle-to-cycle spread instead of tuning to the limit.

Raising acceleration raises kinetic energy and stopping distance, so re-run the cell's risk assessment before production: ISO 10218-2, adopted in the US as ANSI/RIA R15.06, requires the integrated application's safeguards to match the speeds and loads actually run.

The decision for each case #

Case Decision
Transfer must finish within 5.00 s Define the interval, measure with two signals, remove removable waits, raise acceleration on acceleration-limited segments - the example reaches 4.89 s
Still over the deadline after motion settings Shorten the route, drop a redundant waypoint, or re-allocate the task between robot and station; a higher speed command is not a fix
The station needs the part exactly on the target Synchronize: add deliberate waiting at an approved sequence point; a wait moves the completion signal, not the physical placement, so pick the event the process actually needs
The cell does not exist yet Estimate in simulation, then confirm with start and completion signals at commissioning

Treat the target as a deadline to measure against, not a number to reach by feel - the two signals tell you which of the two you are actually achieving.

Questions asked

Can the robot controller itself be told the target time?

Robot controllers do not take a target duration as a motion input; the programmer sets speed and acceleration and the time comes out of the trajectory. Some controllers accept an external signal or value that changes the speed data the move algorithm uses - that is a production-rate control across the whole program, useful for matching station takt, not a way to shorten one named transfer.

Can I estimate the cycle time in simulation before the robot runs?

Yes, as an estimate to tune against. One documented workflow (RoboDK's cycle-time guide) is to set the robot's joint speed and acceleration as accurately as possible and add rounding to the paths; a result built on guessed acceleration values will mislead. Treat the simulated value as the starting budget and confirm it with start and completion signals once the cell runs.

The recorded interval disagrees with a stopwatch at the cell - what do I check?

Check the time base first: the subtraction is valid only when both timestamps come from the same clock. If a display value does not update, trace backward from the display binding to the receiving tag or variable, then the communications mapping, then the robot program state. A stale display does not prove the robot failed to emit the event, and a moving tag does not prove the event fires at the agreed physical boundary.

Does a moving-conveyor pickup change how the 5 seconds is timed?

The measurement method is identical, but the definition changes: the robot coordinates with a moving part, so readiness conditions add waiting time that varies from cycle to cycle. Expect a spread of measured values rather than one repeatable number, time the coordinated transfer separately from any fixed-position transfer, and set the deadline against the worst realistic spread, not the best cycle.

Keep reading

  • Explainer

    Why a robot needs a servo controller between it and the motor

    A robot cannot drive a servo motor through its network port; the motor needs a drive and positioning controller in between. For indexed work — four preset positions, each complete before the robot cuts — the controller stores the positions, takes a trigger over a documented protocol such as Modbus/TCP, and reports confirmed position and completion. A successful connection proves transport, not motion.

    Servo and stepper motion

  • Explainer

    Robot Tending a CNC Lathe Over a Simple I/O Handshake

    Almost any CNC lathe whose control offers spare M-code-mapped outputs, spare inputs that can gate cycle start, chuck clamp control, an automatic door and a wait-on-input can be robot-tended over a sequential handshake. The lathe asks, the robot loads or unloads and answers done, and the program resumes. Simultaneous robot-and-cutting motion is a separate integration project.

    Servo and stepper motion

  • Selection guide

    What Decides a Plasma Table Retrofit That Keeps the Original Servos

    Identify each servo drive's command and feedback interfaces before you buy anything: interfaces, not motor age, set the retrofit boundary. Keep the motors and drives when the new control chain can generate the command each drive accepts — commonly a ±10 V analog speed or torque signal — reproduce the enable, fault and limit lines, and close every position loop with valid feedback. If a drive's interface cannot be identified, replace that drive; keep the motor only when the replacement drive matches its ratings and feedback.

    Servo and stepper motion